Project Details

Owner: Sound Transit

Contract value: $12,000,000

Description

The work being performed on this project includes the demolition of two existing guard shacks and miscellaneous asphalt pads. The new construction consists of the installation one new layover track where Sound Transit trains will be serviced. There will be installation of four new buildings. These buildings include two bullet proof guard shacks, a storage facility, and a modular building for the crews that will be servicing the trains. There will also be new paving that will be installed on the site. The paving is broken down into four access roads (North Access Road, Center Access Road, East Access Road, and South Access Road). In addition to the roads there will be a paved parking lot for the modular building and paved driveways to the storage facility and the air compressor pad.