| PROJECT: | ||
| LOCATION: | San Francisco, California | |
| OWNER: | Clean Water Program, City of San Francisco Public Works Department | |
| CONTRACT VALUE: | $46,498,338 | |
| CONTRACT TYPE: | Unit Price | |
| OWNER CONTACT: | Manfred Wong | Phone: (415) 431-9430 |
| ENGINEER CONSULTANT: | N/A | |
| ENGINEER CONTACT: | Pieter Toal | Phone: (415) 431-9430 |
| PROJECT MANAGER: | Michael Strandberg | Phone: (510) 293-1100 |
| START DATE: | September 1992 | |
| COMPLETION DATE: | July 1995 | |
Description of Work:
Shimmick Construction Company along with its Joint Venture Partner, Obayashi
Corporation Inc., successfully completed this very large and complicated
underground box sewer in the City of San Francisco. This project was one of five
projects that together made up the Islais Creek
Facilities. The Islais Creek Facility is for the storage of combined (rain water
and sewage) sewage during wet weather in the City of San Francisco. San
Francisco has an unique problem in that its storm water and its sewage utilize
the same underground pipelines. Because of this, whenever it rains the San
Francisco sewage treatment plants
get overwhelmed with the amount of sewage that
they must process. So much so, in fact, the City releases untreated sewage to the
bay and the ocean during some storms because it is just too much flow for the
system to treat. The Islais Creek Project provided a large underground storage
facility in order to “buffer” the large amounts of rainwater so that the number
of overflows of raw sewage would be minimized and the stored sewage/rainfall
could be treated at the capacities of the existing treatment plants.
Contract “C” is a 6,000 feet long underground cast-in-place-concrete box
structure. The box varied from 40 feet deep and 27 feet wide to 25 feet deep and
16 feet wide. The structure was built inside a shored excavation. The shoring
for the excavation varied depending on the geotechnical characteristics of the
ground. Because t
he
project site was so long, the soil characteristics varied a great deal. In some
areas, very large and long interlocking sheet piles were used as the shoring
walls. The sheet piles were supported by a waler and strut system made from wide
flange and H-pile sections. In another portion of the structure, the excavation
shoring consisted of rock bolts and shotcrete. Furthermore, another portion of
the structure had soldier pile and lagging as the means of excavation support
with the same type of waler and strut system as the sheetpile area.
The structure was constructed from the bottom up with a series of concrete form travelers. The box was constructed on two separate headings, the 27 feet wide heading and the 16 feet wide heading. First the invert was poured in 50 feet long sections, then the walls were poured all the way to the soffit, lastly the soffit was poured. Once the structure was complete, it was backfilled with soil approximately 4 to 12 feet deep. Surface improvements were than constructed to rebuild the area.
Many storm drain tie-ins to the existing sewage and storm drain systems were constructed to link the new storage box. Also many new storm drain lines and water lines were relocated to provide the right-of-way for this storage box to be constructed. To further complicate this project, most of the construction took place in the middle of the busy streets in San Francisco’s Bay View / Hunters Point Area.