Headquarters
Headquarters
National
Northwest
Southwest
O&M
MEP
Legacy Foundations
510-777-5000 8201 Edgewater Drive Suite 202 Oakland, CA 94621
303-694-2770 7601 Technology Way Suite 100 Denver, CO 80237
707-759-6858 1 Harbor Center, Suite 200 Suisun City, CA 94585
949-333-1500 530 Technology Dr Irvine, CA 92618
954-350-1232 10276 NW 47th Street Sunrise, FL 33351
949-333-1500 530 Technology Dr Irvine, CA 92618
949-333-1500 530 Technology Dr Irvine, CA 92618
MAKE IT HAPPEN.

Soledad Wastewater Treatment Plant

Home > Markets > Water/Wastewater Treatment > Soledad Wastewater Treatment Plant

Soledad Wastewater Treatment Plant

The Soledad Wastewater Plant consisted of three sets of ponds, including aerated ponds, secondary ponds and a polishing pond. The upgrade and expansion converted the former location into a mechanical plant that includes headworks pretreatment, primary, secondary, tertiary and residuals treatment. The plant effluent was used as reclaimed water or flows to rapid infiltration basins for disposal. Plant solids flowed to stabilization basins for thickening, then to a screw press system for dewatering, before moving into drying beds.

The plant was made up of 23 unique structures and building areas including headworks, biological nutrient removal (BNR), aeration, clarifiers, pump stations, flocculators, filters, ultraviolet disinfection, chemical/polymer injectors, and solids drying.  Included within these areas was specialized equipment that consisted of the following: grit removal system, compressible media filtration system, ultraviolet disinfection, and a screw press system for dewatering sludge.  These features were interconnected by 7,000 linear ft. of process piping and monitored by electronic devices, programmable logic controllers (PLC) and SCADA.

Several key construction activities were critical to the successful and timely completion of the project. A soil-bentonite wall was installed around the perimeter of the open excavation to allow a system of dewatering pumps to lower the water table below the construction. Shimmick’s value engineering proposal avoided most of the shoring originally required on the project and provided a significant credit to the owner. Stone columns were used to compensate for the liquefiable soil in areas where it was too close to levees to excavate and replace the soil under some of the structures.

Project Details

Location:Soledad, CA
Amount: $49.7M
Delivery Method:Bid-Build
Client Name:City of Soledad
Duration: 2008–2011