Headquarters
Headquarters
National
Northwest
Southwest
O&M
Electrical
Legacy Foundations
833-723-2021 530 Technology Dr, Suite 300, Irvine, CA 92618
833-723-2021 7601 Technology Way Suite 100 Denver, CO 80237
833-723-2021 1 Harbor Center, Suite 200 Suisun City, CA 94585
833-723-2021 530 Technology Dr, Suite 300, Irvine, CA 92618
833-723-2021 10276 NW 47th Street Sunrise, FL 33351
833-723-2021 530 Technology Dr Irvine, CA 92618
833-723-2021 530 Technology Dr Irvine, CA 92618
MAKE IT HAPPEN.

West Howe Street Bridge Seismic Retrofit

Home > Markets > Transportation > West Howe Street Bridge Seismic Retrofit

West Howe Street Bridge Seismic Retrofit

As part of the Levy to Move Seattle, 16 bridges were selected for seismic retrofits, including the West Howe Street Bridge. The West Howe Street Bridge was constructed in 1946 prior to the modernization of the seismic design code. The bridge provides a more direct connection across 32nd Ave W to the neighborhood located along the southwest edge of the Magnolia community.

Shimmick’s work addressed seismic deficiencies of the bridge structure. The retrofit included clearing and grubbing, steel column strengthening, steel bracing strengthening, column base strengthening, gusset plates, replacing existing rocker bearings with elastomeric bearings, seat extension and a catcher block at the west and east abutment, and stop block at each side of the stringer at the east abutment.

The original contract drawings outlined the steps to replace the existing rocker bearings with elastomeric bearings during the span of two weekend bridge closures. Shimmick developed and engineered a jacking plan that allowed us to replace all five bearings in one weekend. The plan included using high early concrete and grout mixes to ensure the required strength was met during one weekend to allow traffic back on the bridge. Shimmick also developed a contingency plan that allowed traffic back onto the bridge if the completion of the bearing replacement was not accomplished in one weekend. By creating this detailed plan, Shimmick was able to remove and replace the bearings in one weekend instead of two, which was a substantial cost saving for the project.

Project Details

Location:Seattle, WA
Amount: $4.2M
Delivery Method:Bid-Build
Client Name:City of Seattle
Duration: 2019-2021